Gantt Chart
Enter the activities below and produce
the Gantt chart.
TASK/ACTIVITIES DURATION
1. PLANNING Phase
Select group members 1 day
Define problem 1
day
Produce Project schedule 1
day
Calculate project feasibility 1
day
---------
2. ANALYSIS Phase
Gather
information 3
days
Define
Systems Requirements 3 days
Write
the proposal Document 3
day
Send
proposal Document 0
day
Draw
logical DFD 3
days
--------
3. DESIGN Phase
Design
current process 3 days
Design
new process 5
days
Design
Data Base 5
days
Design
Interface and forms 5
days
Send
Design Documents 0
day
--------
4. IMPLEMENTATION PHASE
Do
Coding 8
days
Do
testing 3
days
Do
Acceptance Test 2
day
Write
Report Document 5
days
Do
Final Class Presentation 0
--------
TOTAL NO. OF DAYS (PROJECT DURATION TIME ) 52 days