Network Diagram and Critical Path - Answer
1. Using Microsoft Project create a Network Diagram for the activities below. What is its critical path ?
2. A diagram below represents the Interviewing Activities of a systems development initiative.
List all the Paths for the Network diagram and determine its Critical Path.
Possible Path:
A-B-C-E-H = 8 Days
A-B-C-F-I = 10 Days
A-B-C-G = 6 Days
A-B-D = 3 Days
Critical Path: