Assignment 4b CBA
Assignment 4b on
ECONOMIC FEASIBILITY
1. Consider the
information given below AND ANSWER the questions following it:
Development Costs
Hardware RM 350,000
Software RM 70,000
Training RM 15,000
Annual Production Costs
Supplies RM 4,500
IS personnel RM 56,000 in year 1; 8% annual increase
Maintenance RM 15,000 per year
Labor savings RM 45,000 in year 1; 5% increase annually
Increase sales RM 80,000 in year 1; 10% increase annually
Assumptions:
Discount rate 12 %
Sensitivity factor (costs) 0.10
Sensitivity factor (benefits) 0.6
Questions:
- Create
a cost-benefit analysis table (for 4 years) to assess the economic feasibility
of the proposed system.
- What
is the profitability index computed for this project?
- Do
you recommend that the organization fund this development project? Why and
why not?