Assignment 4a CBA

Assignment 4a:  USE YOUR KNOWLEDGE TO COMPUTE THE ECONOMIC FEASIBILITY OF THE CASE BELOW


1.         Consider the information given below AND ANSWER the questions following it:
                                                                                                           

Development Costs
Hardware                    RM 20,000
Software                     RM 10,000
Training                       RM   8,000

Annual Production Cost
Supplies                       RM   1,500
IS personnel                RM 30,000 in year 1;    10% annual increase
Maintenance                RM   3,000 per year

 

Expected Annual Benefits
Labor savings              RM 20,000 in year 1;   5% increase annually
Increase sales              RM 25,000 in year 1;   10% increase annually

Assumptions:
Discount rate                           15 %
Sensitivity factor (cost)           0.5
Sensitivity factor (benefit)      0.9



Questions:
  1. Create a cost-benefit analysis table (for 4 years) to assess the economic feasibility of the proposed system.

  1. What is the profitability index computed for this project?

  1. Do you recommend that the organization fund this development project? Why and why not?