Network Diagram and Critical Path - Answer



1.    Using Microsoft Project create a Network Diagram for the activities below. What is its critical path ?







  2.    A diagram below represents the Interviewing Activities of a systems development initiative.



List all the Paths for the Network diagram and determine its Critical Path.


Possible Path:
A-B-C-E-H = 8 Days
A-B-C-F-I = 10 Days
A-B-C-G = 6 Days
A-B-D = 3 Days


Critical Path:
A-B-C-F-I  = 10 Days

------------------------------


Download Link


1. Network Diagram 

2. Assignment 3       
Learn more »

Network Diagram and Critical Path


     1.    Using Microsoft Project create a Network Diagram for the activities below. What is its critical path ?



     2.    A diagram below represents the Interviewing Activities of a systems development initiative.


List all the Paths for the Network diagram and determine its Critical Path.

Learn more »